Boundary Wall Calculator

Estimate above-ground bricks, mortar and plaster from your wall measurements. Add your quoted rates for costs.

No layout needed

Calculation details

Update the example values below.

01Measurements
ft
ft
ft
Example: every 10 ft. Use approved spacing; pillar materials are excluded.
ft²
Subtract areas within the measured wall length that are not brick infill.
02Material detailsSizes, quantities and editable allowances.

Use the brick size and mortar specification for your site. Pillar materials and foundations are excluded.

mm
mm
mm
mm
sand parts
%
%
×
mm
ft²
For exposed pillar faces already deducted from masonry. Do not add gate openings back.
sand parts
%
ft³
100 ft³ is an editable example. Confirm actual capacity with your supplier.
03Rates (optional)Enter your supplier and labour quotes.

Leave blank for quantities only. Use 0 only for costs included elsewhere or free. No market prices are assumed.

INR / brick
INR / bag
INR / ft³
INR / m³
INR / m²

How this is worked out

Check the formulas, allowances and scope before buying.

From measurements to materials

Net wall area = length × height − gate/opening and pillar-face deductions. Masonry volume = net area × thickness.

Brick count = masonry volume ÷ brick module volume (each brick dimension + joint). Apply brick wastage, then round up.

Wet mortar = masonry volume − theoretical brick count × solid brick volume. Dry mortar = wet mortar × dry-volume factor. Split it 1:sand ratio; apply mortar allowance.

Plaster area = (net wall area + additional plaster area per side) × selected sides. Additional area can include exposed pillar faces deducted from masonry. Wet plaster = area × thickness; apply the dry-volume factor, plaster ratio and allowance.

Cement uses 1,440 kg/m³ and 50 kg bags. Round masonry and plaster bags up separately. Add their sand volumes; 1 m³ = 35.3147 ft³.

Pillar reference = rounded-up(length ÷ spacing) + 1, including two ends of one open run. Corners, gates, existing supports and closed boundaries change this count.

Assumptions to check

Above-ground infill masonry and selected flat plaster only. Deduct pillar faces from masonry if included in the measured length; add any pillar-face plaster separately. Pillar concrete, foundations, footings, steel, coping, gates and painting are excluded.

Pillar spacing and wall thickness are supplied quantity inputs, not structural recommendations. Use approved site details.

Trolley capacity varies; confirm the entered capacity with your supplier. Trolley figures are volume equivalents, not rounded delivery loads.